Norwegian power generator Statkraft opens its first solar power plant, Casale in Aprilia, Italy. Statkraft also reports an agreement with Siemens Energy to build more solar power plants in Italy.
With a total capacity of 3.3 MW and an annual power production of 4.5 GWh, the Casale solar park will supply approximately 1200 Italian households with renewable energy.
“Developing solar power is part of our strategy to maintain Statkraft’s role as Europe’s largest renewable energy company”, said Bård Mikkelsen, President and CEO of Statkraft.
Statkraft also declares an exclusive framework agreement with Siemens Energy to build up to 40 MW new solar power capacity in Italy during 2010. The agreement covers Statkraft’s project pipeline in Italy and construction of the next solar plant is expected to commence in spring 2010.
Following a comprehensive procurement process involving a number of suppliers, Statkraft has chosen Siemens Energy as an exclusive EPC contractor in Italy. As Engineering Procurement Construction (EPC) contractor, Siemens will handle engineering, project management and turnkey construction of the photovoltaic plants. Siemens will also be responsible for operation and maintenance for the first five years.
“Siemens Energy is a highly competent partner, securing our ability to build several solar parks in parallel and reach the target of commissioning new solar parks before the end of 2010. The time schedule is of great importance, due to the uncertainty regarding future support schemes for solar power,” says Olav Hetland, senior vice president solar power in Statkraft.
“After successful execution of the Casale project for Statkraft, we are continuing our cooperation with the implementation of further solar energy projects in Italy,” said René Umlauft, CEO of the Renewable Energy Division of Siemens Energy.
Tags:
Statkraft
Add a Comment to this Article