Jumbo has successfully completed the TP-installation for the Anholt Offshore Wind Farm, off the Danish coast. Jumbo’s DP2 Heavy Lift Vessel Jumbo Javelin installed the 111 TP’s with a record-breaking installation rate of 3 TP’s per day.
The transport, installation, access to the TP’s and grouting was done without any Lost Time Injuries (LTI=0). Once again Jumbo proved to have a very safe and efficient concept for the transport and installation of wind farm foundations with the use of only one free floating vessel on DP.
Jumbo’s scope of work included transport and installation of 111 TP’s. The TP’s, weighing up to 180t each, were loaded in Aalborg, Denmark and transported to the offshore location on board the Jumbo Javelin.