Winstar provides update on Tunisian operations

Winstar Resources Ltd. provides an update on the following; initial test results from Chouech Essaida Silurian #10 well (CS Sil #10) in southern Tunisia, well workover plans at Chouech Essaida Concession in southern Tunisia, termination of Sabria Concession (in central Tunisia) farmout negotiations, field operations in northwest Romania and January 2012 production.

Chouech Essaida Silurian #10 ("CS Sil #10") (100% working interest) Southern Tunisia

This well rig released on December 10, 2011, at a total depth of 4,420 meters with objectives in the Triassic and Silurian levels. The rigging down of high pressure testing equipment began on February 1, 2012.

Drilling, completion and testing have been on time and within budget at an estimated cost of US$17 to $18 million, which translates into after tax cost of US $ 11 million net to Winstar.

Silurian

The Silurian primary target is the Tannezuft Sandstone which was intersected 30 meters structurally higher and 40% thicker (gross 32 meters) at CS Sil #10 than the equivalent producing sandstones at Chouech Essaida Sil #1 ("CS Sil #1") approximately 2 kilometers away.

Initial CS Sil #10 tests, indicated that the Tannezuft Sandstone is predominately 45 degree API crude oil saturated (25 gross meters) and also contains rich natural gas yielding 55 degree API condensate (7 gross meters). CS Sil #1 produces gas condensate only, which was therefore expected in CS Sil #10. At 4,300 meters, Tannezuft crude oil at CS Sil #10 is believed to be the deepest crude oil tested in Tunisia to date.

The Tannezuft sands at CS Sil #1 and CS Sil #10 wells have similar porosity and permeabilities as calculated by open-hole logs and Modular Dynamic Formation Tests (MDTs). The test results of the Tannezuft sand at CS Sil #10 are not conclusive; crude oil, gas and condensate were recovered at surface but build-up data indicates that crude oil flow rates may benefit from further clean-up or stimulation. Production strategy is being evaluated.

The 32 gross meters of Tannezuft sands are considered to be a potential, crude oil and gas condensate resource.

Triassic

At CS Sil #10, the Company identified four separate potential Triassic TAGI Sandstone oil zones as calculated by open-hole logs and MDTs. Two zones (total 3 gross meters) have been perforated and tested. Test results are inconclusive but potentially indicate a completion (mechanical) or reservoir issue. The tests are recording small amounts of crude oil with water of much higher salinities than typical Triassic oil producers within our concession. Remedial strategy is being evaluated.

Well workover plans (100% working interest) Chouech Essaida, Southern Tunisia

Pump equipment will be installed in Chouech Essaida #11 and Chouech Essaida #12 in February or early March 2012. Expected incremental production from these two Triassic TAGI Sandstone oil wells is 300 to 375 barrels of oil per day ('bopd') plus solution gas.

Sabria Concession (45% working interest) Central Tunisia

The Company advises that negotiations with a private European exploration company ("PrivateCo") to farmout half of its 45% working interest in the Sabria Concession as described in the August 18, 2011 press release have been terminated.

Subject to further internal review and approval by Winstar's 55% working interest partner, ETAP (The Tunisian State Oil Company), the Company is prepared to drill a new 4,000 meter deep Ordovician Hamra Sandstone test during the current year.

Romanian Exploration Wells (60% working interest) Satu Mare Concession, Northwestern Romania

Winstar's 1,600 meter deep Moftinu 1000 well, was drilled and cased during late January 2012, on time and within budget. We are pleased to report that the well encountered 10 gross meters of Pliocene sands charged with natural gas, and 2 gross meters of gas bearing Miocene sand, as indicated by strong shows during drilling and open-hole logs. Testing of these two zones should be completed during February 2012.

The Moftinu 1000 well is only 1.5 kilometers away from a regional low pressure natural gas transmission line. Further to positive test results and a review with its partner Rompetrol Group N.V and the Romanian government, the Company hopes to place the well on a long term production test by connecting to the regional transmission line. Romania currently has regulated gas prices, but the government has pledged to eliminate subsidies by 2015.

Winstar's 1,600 meter deep Madaras 109 well was drilled and cased in late 2011, on time and within budget. Well testing should begin this month. A dolomitic oil zone (2 gross meters) in the Lower Miocene will be stimulated by acid wash. A Middle-Miocene sandstone (15 gross meters) which appears from open-hole logs to be oil saturated will also be evaluated.

Further to positive test results plus a review with its partner Rompetrol Group N.V and the Romanian government, the Company hopes to place the well on a long term test. Oil may be sold either by trucking crude to rail spurs with off loading facilities or directly to local refineries. Crude oil in Romania is sold at prices linked to Brent or Ural oil posted prices.

The Moftinu and Madaras wells were drilled by Winstar as the operator of the Satu Mare Concession. Winstar pays 100% of the costs of these wells, estimated at US $ 4 million, to earn a 60% working interest in the gross 728,960 acre Satu Mare Concession under a Farm-in Agreement with the Rompetrol Group N. V. of Romania.

Tags: Winstar Resources Ltd.




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml