Technip received instructions from Anadarko Petroleum Corporation to begin the engineering, construction and transport of a 23,000-ton Truss Spar hull for the Heidelberg field development. This field is located in the U.S. Gulf of Mexico, at a water depth of 5,310 feet (1,620 meters).
The Letter of Intent allows Technip to begin construction work on the project and other early works including purchase of long-lead items for the hull and start of fabrication, in advance of the expected project sanctioning around mid-2013, after which it will enter into Technip's backlog.
The Heidelberg Spar will have a capacity of more than 80,000 barrels of oil and 2.3 million cubic meters of natural gas per day.
Technip's operating center in Houston, Texas will provide the overall project management and engineering. The detailed hull design and fabrication will be carried out by Technip's construction yard in Pori, Finland where most of Technip's Spar projects have been manufactured.
Tags:
Technip
Add a Comment to this Article
Please be civil. Job and promotion will not be added into the comment page.