Drillsearch Energy Limited says that Beach Energy Ltd (operator) of the PEL 91 Joint Venture has advised that the commissioning of the Bauer-to-Lycium Crude Oil Pipeline is commencing next week. The PEL 91 Joint Venture is comprised of Drillsearch (60%) and Beach Energy as Operator (40%).
Beach as Operator of the PEL 91 Joint Venture has advised that it will commence commissioning of the Bauer-to-Lycium oil export pipeline during the week starting Monday, 22 April 2013.
The initial installed capacity of the oil export pipeline is 10,000 barrels of oil per day. Filling of the pipeline is scheduled to commence late in the week. Ramp up to full operation of field production facilities and pipeline oil exports is expected to reach approximately 10,000 barrels of gross oil per day by the first week of May 2013.