Silvermere report further progress with the tie-in of the I-1 well


Published Aug 20, 2012
Silvermere Energy

Silvermere report further progress with the tie-in of the I-1 well in its Mustang Island 818-L Field. This is based on information provided by the Operator, Dominion Production Company LLC (Dominion).

The pipeline installation was completed on 10th August 2012 and the sub-sea tie-in was completed and tested on 15th August. All sub-sea valves have been opened ready for flow and the overall installation project was substantially completed on 18th August.




   