Imperial Resources, Inc. and its wholly owned subsidiary, Imperial Oil & Gas, Inc. report that testing of the rebuilt Green Tide Salt Water Disposal Facility (SWDF) is progressing well.
On Tuesday July 24, 2012 the SWDF recirculated approximately 360 barrels of water through most of the system to test the integrity of the new plumbing. The Company was able to test all but the final flow lines to the main pumps and with one exception (the offloading lines) all leaks were located and corrected. The two offloading lines were found to be structurally deficient and have been re-engineered using replacement components and will now be tested.