ExxonMobil Production Company has mobilized the drilling rig for the Point Thomson Project.

The rig, owned by Nabors Alaska, has been upgraded to drill the high pressure wells at Point Thomson. It was moved from Deadhorse to the drilling site in modules, some weighing more than one million pounds.

As there are no permanent roads to Point Thomson, Fairweather E&P Services Inc. and Nanuq/AFC constructed over 30 miles of ice road to enable the transport of heavy equipment and materials while protecting the North Slope environment. Most of the ice road follows the shore line along the Beaufort Sea.

The Alaska Department of Natural Resources (DNR) authorized the ice-road permits on January 27, allowing mobilization of the drilling rig and provided guidance to other regulatory agencies to expedite permitting to allow drilling to begin.

Craig Haymes, Alaska production manager for ExxonMobil, said, "We are moving forward with drilling and development activities at Point Thomson, for the mutual benefit of Alaskans and the Point Thomson Unit working interest owners. DNR staff and other local, State and Federal agencies have worked tirelessly to process permits necessary to allow drilling to begin. We are on schedule to begin production at Point Thomson by year-end 2014 and look forward to working with the State to resolve the remaining Point Thomson issues to ensure the project schedule is not impacted. Construction crews recently completed the final installation of camps and support facilities at the existing gravel pad to accept the rig. Over 250 people will work on these drilling operations, with an average of over 500 people at year-end 2014, when we expect to begin production.”

The initial phase of the project will process approximately 200 million cubic feet per day of Point Thomson gas in order to produce approximately 10,000 barrels per day of liquid condensate into the Trans Alaska Pipeline System by year end 2014. The remaining gas will then be recycled into the Point Thomson reservoir. The Point Thomson Unit working interest owners committed $120 million to the drilling and development activities in 2008, with additional investments of about $250 million expected in 2009.

Tags: ExxonMobil Production Company




   

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml


 

Home