MEO provides update on Zeus-1 timing


Published Dec 12, 2008
[an error occurred while processing this directive]

Edit page New page Hide edit links

MEO spuds the Heron-2 well

MEO has advised the following update on the timing of drilling Zeus-1.

The latest advice MEO has received currently forecasts a release of the Songa Venus drilling rig on approximately December 23, 2008. This release date remains subject to ongoing decisions in relation to production testing and/or further drilling operations of the Ichthys North well. Upon release and acceptance of the Songa Venus by MEO the rig will undertake about a six day tow to the Zeus-1 location in permit WA-361-P.

All regulatory approvals have been received for Zeus-1 drilling and MEO is in readiness to spud Zeus-1. All remaining casing, equipment and materials for Zeus-1 have been delivered to Dampier for progressive load-out to the drilling rig by the Lady Astrid and Lady Caroline anchor handling and supply vessels. The Lady Astrid has been scheduled to transport the equipment and materials for the spudding of Zeus-1 from Broome to the Songa Venus prior to the rig moving to the Zeus-1 location.

MEO is planning to mobilize supervisory personnel to the drilling rig on December 19, 2008 preparatory to handover of the rig.

Tags: MEO Australia Limited




   

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml


 

Home