Neon Energy Limited provides Paloma Deep testing update


Published Dec 6, 2012
[an error occurred while processing this directive]

Edit page New page Hide edit links

Neon Energy Limited

Neon Energy Limited provide the following update further to the ongoing production testing operations at the Company's Paloma Deep oil and gas discovery.

Testing of the Lower Stevens 'B' sand in the Paloma Deep-2 vertical appraisal well has thus far progressed well. The zone of interest was fracture stimulated via high pressure injection of gelled water, infused with a propant (ceramic beads) designed to be deposited within the induced fractures. Initial flow back of fracture fluid has included oil and gas.

To facilitate clean up of the wellbore and initiate an increased and steady flow of hydrocarbons from the reservoir, the 'frac' tubing (3½') is being replaced with smaller diameter (27/8') production tubing. After adding additional perforations to increase the test interval, the well will then be placed on pump; an operation expected to be complete in approximately one week's time. A further announcement will be issued after the well has cleaned up and a stable flow rate has been attained.

Tags: Neon Energy Limited




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us
Stats

 

sitemap xml