Scandoil  

TATNEFT Company constructed an oil pipeline under the Kama River Bed


Published Dec 20, 2012
[an error occurred while processing this directive]

Edit page New page Hide edit links

TATNEFT-2

TATNEFT has put into operation a new pressure oil pipeline "Pervomaysky tank farm - "Naberezhnye Chelny" pumping station of NGDU "Prikamneft" having the designed throughput capacity of 1574.92 thousand tons of transported crude oil per year (135.0 tons per hour).

The project is a single 7.88 km long pipeline consisting of three sections. The length of the section from the right bank of the Kama River from the point of connection with the existing crude oil pressure pipeline "Pervomaysky tank farm - underwater piping" to the pipeline pig launching station is 1.13 km.

Construction of the underwater pipeline in the water area of the Nizhnekamsk reservoir and the Kama River was made under the river bed at a depth of 8 to 10 meters. The underwater pipeline is made from a steel tube 219 x 12 mm with external reinforced insulation thickness of 5 mm. It includes two pipeline strings (primary and standby) of 2.18 km long each from the pig launching station to the pig trapping one.

The length of the section on the left bank of the Kama River (from the pig launching station to the point of connection to the existing interconnecting pressure pipeline UPS "Kyzyl-Tau") made of steel tube 219 x 8 mm is 4.57 km. The pipeline is laid in concrete channel trays along its entire length and it includes a pig trapping station.

Tags: TATNEFT




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us
Stats

 

sitemap xml