Ivanhoe passes halfway mark in drilling program at Tamarack


Published Feb 18, 2010
[an error occurred while processing this directive]

Edit page New page Hide edit links

Ivanhoe Energy agrees to sell interest in LAK Ranch Project-Spotlight

David Dyck, President and Chief Executive Officer of Ivanhoe Energy Canada Inc. says that Ivanhoe Energy has completed over 50% of its 30-well delineation drilling program at the Tamarack project in the Athabasca region of northern Alberta, and expects to complete drilling by mid-March. In addition, engineering tasks related to the Tamarack Heavy-to-Light (HTL) upgrading facility and the upstream facilities are firmly on schedule.

Ivanhoe Energy has three drilling rigs on-site, drilling 24 hours per day. Drilling operations are focused on the centre of the Tamarack lease, the area Ivanhoe Energy has targeted for Phase I development. This area contains top quality, thick, clean oil sands with net pay in the 30 to 45 meter range. The well logs that have been obtained are consistent with data from earlier delineation drilling which indicated that the lease contains clean, very thick oil sands with high oil saturation.

Delineation drilling consists of drilling core-holes in sufficient density to accurately map the characteristics of the reservoir. This program will complete all drilling requirements for Phase I before steam assisted gravity drainage (SAGD) well drilling takes place.

"This delineation drilling program is an important milestone for us," said David Dyck. "Once this program is completed, we will have fulfilled a key requirement to file our regulatory application in mid-2010 for the development of the Tamarack integrated heavy oil project."

Submitting the regulatory application is a key stage-gate, under new US SEC reporting guidelines, to allow Ivanhoe Energy to sequentially migrate portions of its Tamarack asset base in 2010 from the current 441 million barrels of "best estimate contingent resource" category to categories of reserve recognition, such as probable and possible reserves.

The results from this drilling program will be utilized by Ivanhoe Energy's independent evaluator, GLJ Petroleum Consultants, to generate an updated resource report. Based on current resource estimates, Tamarack could ultimately be capable of supporting production of up to 50,000 barrels per day from an integrated HTL facility for approximately 30 years.

Tags: Ivanhoe Energy Inc.




   

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml


 

Home