JKX Oil & Gas reported that gas production from Well 27 has commenced in its Koshekhablskoye Field, Adygea, Russia. The well is now flowing to the gas processing facility and production testing is under way. Reservoir response will be closely monitored before ramping up towards its production plateau.
Well 27 was suspended after initial workover and testing at 13.1 MMcfd on a 36/64" choke in 2009. Mechanical problems downhole, ahead of field start-up in March 2012, led to the well having to be side-tracked and re-completed. The Geostream KES-536 rig has now moved to well-20 and begun a workover and re-completion operation.