Circle Oil in Morocco

Circle Oil provides the following update regarding its operations and forthcoming work programmes for 2013 in its operational areas of Morocco, Egypt, Tunisia and Oman.

Morocco

• Six well drilling programme planned for H1 2013 in the Sebou and Lalla Mimouna Permits • Over 50% increase in gross production from 4.5 MMscfd to between 6.5 and 7.0 MMscfd planned in Q1 2013 • Preliminary interpretations of Lalla Mimouna 3D seismic survey encouraging, with wells in the 2013 programme aiming to provide substantial additional reserves • Third offtake agreement added 22 December 2012 for initial additional US$0.5 Million per annum

Egypt

• Four well drilling programme comprising of one producer and three injector wells planned from now through to the end of July 2013 • Gross production averaging 9,091 bopd for January 2013 • Additional production now on stream from 12 February 2013 with the start up of associated gas production at an initial rate of 9 MMscfd (1,638 boepd ) • AASE-14 ST2 to be tested and hooked up as another additional producer by end February 2013 • Gas processing expected to provide an additional 140 - 150 bocpd and 35 tonnes of LNG (c. 400 boepd) per day

Tags: Circle Oil plc




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us
Stats

 

sitemap xml