Cliff Head field production temporarily halted


Published Feb 25, 2011
[an error occurred while processing this directive]

Edit page New page Hide edit links

Roc Oil provides drilling activity update

ROC advised that production from the Cliff Head oil field, offshore Western Australia, in which its subsidiary, Roc Oil (WA) Pty Ltd, holds a 37.5% participating interest, has been temporarily suspended since February 17, following advice from BP that it had identified organic chloride in Cliff Head crude delivered to the BP refinery on February 15. ROC understands that the organic chloride may have been related to batch chemical treatments being undertaken as part of the current Cliff Head 12 well workover.

To facilitate the restoration of crude production and export, a flushing program has been conducted to clear the Cliff Head production system of any potential residual organic chlorides. There have been no losses of containment or environmental incidents as a result of this activity. Regulatory authorities have been informed of the temporary shutdown in accordance with requirements. Prior to the suspension, Cliff Head production was at reduced levels because of workover activity and was averaging approximately 3,000 BOPD.

ROC considers that the Cliff Head field is now ready to return to production, pending resolution with BP. ROC will advise the market once production from the Cliff Head field has recommenced.

Tags: ROC Oil




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml