Scandoil  

HANSA HEAVY LIFT Delivers 13 Modules from China to Australia for Port Pirie Redevelopment Project


Published Aug 10, 2017
[an error occurred while processing this directive]

Edit page New page Hide edit links

HANSA HEAVY LIFT has transported 13 modules - China to Aus
HANSA HEAVY LIFT has transported 13 modules measuring over 147,124 cbm from China to Australia, to help with the redevelopment of the Nyrstar Smelter in Port Pirie (photo: HANSA HEAVY LIFT)

HANSA HEAVY LIFT has transported 13 modules measuring over 147,124 cbm from China to Australia, to help with the redevelopment of the Nyrstar Smelter in Port Pirie.

The cargo was loaded on four separate voyages at the Yanda Module Yard in Jiangsu, China, with the largest piece weighing 690 metric tonnes, and measuring 28 metres in length, 17 metres in width, and 26.7 metres in height.

“This was a particularly challenging project which required the use of three of our vessels on four separate trips operating at their full capacity, including HHL New York, HHL Lagos, and HHL Valparaiso,” says Henry Woo, Head of Asia-Pacific (APAC), HANSA HEAVY LIFT.

“Lifting and rigging were particularly challenging for this project due to the height of the modules combined with the offset centre of gravity, with up to five lifting beams required for a single lift. Our team of in-house engineers managed this by developing innovative rigging solutions as well as enacting a careful loading and engineering plan,” adds Woo.

The decks of each vessel were extended to the aft and in some cases even to the starboard side to accommodate up to five modules per trip.

The over dimensional cargo required the installation of additional bow radars and the extra crew to double up bridge watches.

Due to the sensitivity of the structures and expected rough seas during the voyages, the lashing and securing of the cargo represented another challenge.

Such sensitivity required new types of sea fastening that had to be tested and certified by HANSA HEAVY LIFT. Further measures were put in place to minimise the impact of the obstructed view from the wheelhouse.

Crews also faced strict draft limitations and narrow navigation channels on both ends of the voyages. Modules had to be placed carefully onto the self-propelled modular transporter with minimum clearance in between each vessel’s hull and the fixed structures on the wharf to overcome the limited space on the jetty in Port Pirie.

Loading took place under adverse weather conditions in China, which included snow, rain, and freezing temperatures. At the port of discharge, crews had to deal with temperatures of up to 45° C in Port Pirie.

“We are proud to have completed the project with a smooth execution at every stage, resulting in a safe and on-time delivery of all modules,” says Jens Grever, Head of Cargo Management, Asia, HANSA HEAVY LIFT.

The Port Pirie Redevelopment Project will convert one of the world’s largest primary lead smelting facilities, operated by Nyrstar, to a multi metals processing and recovery facility.

Ben Williams, Project Co-ordinator, from Geodis adds that HANSA HEAVY LIFT demonstrated a “very high level of engineering expertise and professionalism” throughout the entire process, from planning to delivery at the port of discharge.

“HANSA HEAVY LIFT took every detail into consideration, as well as keeping a clear and open line of communication throughout, once again proving themselves to be a reliable super heavy lift partner,” says Williams.

HANSA HEAVY LIFT specialises in the super heavy lift 900+ tonnes industry, delivering best-in-class engineering solutions to customers, particularly in the subsea, oil and gas, as well as the offshore wind farm sectors.

Tags: HANSA HEAVY LIFT




Advertisment:

Comments on this page are closed.

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us
Stats

 

sitemap xml