Scandoil.com

Lukoil continues offshore construction at Yuri Korchagin field in the Caspian Sea


Published Jul 21, 2009
[an error occurred while processing this directive]

Edit page New page Hide edit links

Yuri Korchagin field

Lukoil has launched the next stage of offshore construction operations at Yuri Korchagin field located in the Russian sector of the Caspian Sea.

This stage includes loading on barges, transportation and assembly of the single-buoy mooring (SBM) elements, i.e., jacket and topside, at a distance of 58 km from the offshore ice-resistant fixed platform.

SBM and the offshore ice-resistant fixed platform shall be joined with a 300-mm diameter subsea pipeline, which has already been laid on the seafloor and is ready to be connected to these facilities.

The sea depth at the SBM assembly point is 20.5 meters. The SBM elevation above the sea level is 27.2 meters, the weight is 1,725 tons. The SBM jacket shall be fixed to the seafloor with five 2,130-mm diameter piles.

Following SBM assembly, a floating storage unit with the deadweight of 28 thousand tons shall be moored to it by means of custom devices.

As previously reported, at the end of May an offshore ice-resistant platform with living quarters and a helideck had been assembled at the field. Transportation of the offshore ice-resistant platform with the drilling facilities is scheduled for the end of July. Later, these facilities shall be connected by means of a 74.2-m cross-over bridge.

Tags: Lukoil




   

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml


 

Home