MEO Australia provides update on NT/P68 (Blackwood/Heron)


Published Dec 26, 2011
[an error occurred while processing this directive]

Edit page New page Hide edit links

MEO Australia - NT/P68 (Blackwood/Heron)

MEO Australia Limited provides the following update with respect to activities being carried out by the permit operator, Eni Australia Ltd, in NT/P68.

Bathurst 3D Seismic Survey The CGG Veritas seismic vessel, M/V Veritas Viking II commenced acquisition of the 698 km2 Bathurst 3D Seismic Survey on 3rd December 2011. The survey, over the Blackwood East area of the permit was 52% complete as of 19th December with a total of 363 km2 of full fold 3D coverage recorded.

Heron-3 Timing Update The 15th December 2011 Ensco plc Fleet Status Report indicates that the handover of the Ensco 109 jack-up drilling rig to Eni for drilling of the Heron-3 well is expected to occur in June 2012. The new handover date reflects the later end date of the work program underway by the current rig contractor.

Tags: MEO Australia Limited




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml