Nexen provides Long Lake oil sands project update


Published Dec 10, 2009
[an error occurred while processing this directive]

Edit page New page Hide edit links

Nexen provides Long Lake project update-2

Nexen continues to see positive results at Long Lake following the successful completion of the turnaround program in September. As we move into 2010, our priorities include the ramp up of Long Lake, sanctioning our discoveries in the North Sea, the continued improvement of our Horn River shale gas returns, the development of our offshore Usan project and ongoing exploration in our core areas.

Long Lake Project Update

At Long Lake, we have achieved a number of major milestones over the past year. Our gasification process is working as designed, creating a low cost fuel source which reduces our need to purchase natural gas for operations. Once the project is fully ramped up, it generates a significant margin advantage over our peers and we maintain this advantage even at current gas prices.

The upgrader is fully operational. We are approaching design yields and we have successfully produced over 1.5 million barrels of the highest quality synthetic crude in North America. Upgrader run times are increasing and in November, improved reliability allowed us to process 95% of our bitumen production.

Now that all components of the upgrader are operating as planned, we are focused on maximizing bitumen throughput. We will achieve this by increasing production volumes from our reservoir and by purchasing bitumen from third-parties to enhance returns.

The reservoir is responding to consistent steaming. Following a turnaround completed in September, the reliability of our water treating systems has improved substantially and currently, steam injection rates are at an all-time high of approximately 100,000 bbls/d. We are injecting steam into over 70 well pairs with 50 on production and the remainder circulating steam in advance of becoming producers. This is the highest number of wells that have received consistent steam to date. Prior to the turnaround, steam limitations only allowed us to inject steam consistently into approximately 35 well pairs.

Bitumen production levels are responding to the increased steam volumes and gross production is averaging approximately 17,000 bbls/d. As we start to circulate steam in more wells, our all-in steam-to-oil ratio (SOR) will remain high and is currently approximately 6 with about 20 wells receiving steam but not yet producing bitumen. The SOR of our producing wells is approximately 4.5 and trending down. With the ongoing installation of electric submersible pumps (ESPs), we are seeing improvements in our SORs. We continue to expect a long term SOR of 3 over the life of the project.

Tags: Nexen Inc.




   

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml


 

Home