Oilex provides operational update on Cambay-77H well


Published Mar 25, 2014
Oilex - Cambay field

Oilex Ltd. provides the following information regarding the Cambay-77H well. Drilling of the 12 ¼ inch hole section reached 1,626.5m MD which is approximately 26.5m above the planned casing point for the 9 5/8 inch casing. While pulling out of hole (POOH) to service a mud pump, the Essar Land Rig #4 (Rig) experienced mechanical issues and is currently on equipment downtime at no cost ($0.00 day rate) to the Cambay Joint Venture.

Some of the required replacement parts have been ordered and are being airfreighted from Houston while others have been locally sourced. This reflects the fastest delivery option for special parts not normally included as onsite spares for drilling rigs. It is anticipated the Rig will be operational within 10 - 12 days.

Tags: Oilex Ltd




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us
Stats

 

sitemap xml