Oilex updates flowback operations at Cambay-77H


Published Oct 9, 2014
Oilex - Cambay field

Oilex Ltd says that the chemical treatment and well intervention was completed last month and a significant improvement in recovery rates has been observed.

During flowback operations Oilex Ltd planned to replace the frac tree with a standard production tree. As part of removing the frac tree, two (2) retrievable bridge plugs (RBP) are set in the well as safety barriers against the well flowing. In this instance, the first plug did not set and seal properly and moved downhole where it became stuck. Recovery operations were successfully completed in ~ 13 days.

Subsequent to the operations described above and further chemical treatment, flowback and clean-up again recommenced including recovery of frac water, oil and gas and the well exhibited significantly improved performance.

Tags: Oilex Ltd




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us
Stats

 

sitemap xml