SOCO International provides interim operational update


Published May 17, 2011
[an error occurred while processing this directive]

Edit page New page Hide edit links

SOCO International provides Vietnam update

SOCO provides its Interim Management Statement relating to the period from 1 January 2011 to 16 May 2011.

Overview • Te Giac Trang ('TGT') on track for production commencing in mid-August, plateauing at approximately 55,000 barrels of oil per day ('BOPD') • PetroVietnam has approved the Full Development Plan for the TGT Field including preparations for second phase development drilling which will add approximately 40,000 BOPD to TGT production potential • Te Giac Den ('TGD') licence extension has been granted by the Government of Vietnam and it is expected that seismic acquisition programme will commence in July 2011 • Three exploration wells are planned in Congo (Brazzaville), with the first well on Block Marine XI expected to spud in September 2011

Operations Activity thus far this year has been primarily directed toward bringing the TGT Field offshore Vietnam onstream in August 2011 and in preparing for the three well offshore exploration drilling programme in Congo (Brazzaville), which is targeted to commence in the month of September.

Vietnam

Block 16-1 - Te Giac Trang ('TGT') TGT development drilling continued during the first quarter of 2011 with the completion of the four 'batch' drilled development wells, TGT-4P to -7P, which commenced drilling in 2010. The 2011 development drilling programme for the H1 unmanned platform concluded with the drilling of TGT-8P, the eighth development well. Petrophysical analysis indicates that the wells have confirmed the reservoir model.

All the development wells are suspended and will be perforated to become producing wells on start-up of production, which is scheduled to commence in August 2011. Plateau production during this first phase of development is estimated to be circa 55,000 BOPD.

In May, PetroVietnam, the Vietnamese state oil company, informed the Company that the Government of Vietnam had approved the Full Development Plan for the TGT Field, incorporating the accelerated second phase development with installation of a second unmanned production platform on the H4 fault block. Activities in the field are ongoing with the recent installation of the topsides on the H1 jacket, and the installation of the H4 jacket for second phase drilling and production is complete. The drilling deck on H4 is being installed at this time. The second phase of development drilling is expected to add up to circa 40,000 BOPD to TGT production potential in the summer of 2012.

Te Giac Den ('TGD') The Government of Vietnam's agreement to the extension period for the TGD Appraisal area was also received in May 2011. The initial extension period is from 1 January 2011 to 30 April 2012. An additional six months extension will be automatic (through 31 October 2012) in the event that the Company elects to drill a well. Several 3D seismic acquisition options are currently being reviewed as it is anticipated that acquisition of the 150 square kilometre 3D programme will commence in July 2011.

Ca Ngu Vang ('CNV') At the CNV producing field in Block 9-2 offshore Vietnam, operated by the Hoan Vu Joint Operating Company, negotiations are underway with Vietsovpetro, the operator of the Bach Ho processing facilities, wherein Vietsovpetro would install additional dedicated test separation facilities on the Bach Ho central processing platform complex in order to more accurately measure liquid and gas production from the CNV production stream entering the Bach Ho facilities. The benefit to the Company will be a more accurate allocation of CNV oil, gas and gas liquids production within the Bach Ho production system. CNV production net to the Company's interest has averaged 2,551 barrels of oil equivalent per day during the first four months of 2011.

Africa

Republic of Congo (Brazzaville) Preparations are underway to drill up to three exploration wells offshore Congo (Brazzaville), with the first well expected to spud in early September. A rig has been contracted and is in dry dock for refurbishment prior to spudding the first well. The initial well will drill a pre-salt target on the Marine XI Block with estimated pre-drill unrisked mean recoverable resources of 165 million barrels and should take approximately 45 days to drill. The second well will target the Miocene interval above the salt layer on the Marine XIV Block. With pre-drill unrisked mean recoverable resources of 40 million barrels, the well should take approximately 30 days to drill.

If the first well is successful, an appraisal well is expected to be drilled on the pre-salt target. If not, the final well in this exploration programme will be drilled on a Miocene target in the Marine XI Block with 70 million barrels of pre-drill mean unrisked recoverable resources.

Democratic Republic of Congo (Kinshasa) ('DRC') The security review over Block V in the Albertine Rift in the DRC is ongoing. An initial environmental impact assessment ('EIA') was submitted to the Groupe d'Etudes Environnementales du Congo in March 2011. After a period of review and consultation with stakeholders, including various departments within the Government of DRC, a final EIA was submitted in May.

Outlook TGT is on track to commence production in mid-August 2011. The floating production storage and offloading vessel should be onsite in July. The drilling rig is expected to begin drilling development wells from the H4 platform in September.

If an agreement is reached soon with Vietsovpetro regarding the separation facilities for the CNV production stream, installation of the separation facilities is anticipated to be complete in the early fourth quarter.

Further evaluation of the Nganzi Block, onshore the DRC, is being undertaken, incorporating information gathered in the 2010 drilling programme to better understand the prospectivity of the Block. Remapping of the seismic is underway, focusing on the Chela formation. The exercise will be concluded during the third quarter of 2011 in order to determine the forward programme prior to the end of the initial exploration period.

The Block V project can be progressed into the seismic acquisition stage over Lake Edward upon approval of the EIA report by the Government of DRC. The Company anticipates the review of the EIA report to be concluded prior to the beginning of the third quarter of this year.

The Company continues to evaluate exploration opportunities in South East Asia and Africa. Although it is not guaranteed that any new projects will be introduced in the near term, the TGT oil development in Vietnam is set to transform the cash resources of the Company when it comes onstream in a few months.

Tags: Soco International




Advertisment:

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml