StatoilHydro has been granted consent to upgrade the drilling facility on Oseberg C.
The consent includes the replacement and upgrade of equipment and systems in order to achieve a higher HSE standard and regularity, and provide the foundation for robust and safe drilling until the licence period expires in 2031.
The following main activities are planned:
Clean-up and preparing of areas and systems
Dismantling of existing equipment and systems
Pre-fabrication and procurement of new/modified equipment
Testing of equipment
Shipping and transportation
Installation and connection work
Completion
Operation preparations and start-up
The modifications will be carried out during two downtime periods and are scheduled for completion by the end of May 2011.