Transeuro Energy provides Armenia drilling update

Transeuro Energy Corp provides the drilling of the Kamir 1 well in Armenia. The Kamir 1 is located 65 kilometers west of Yerevan, not far from the Turkish border.

Karmir 1 was drilled to the programmed total depth of 2,346m. A potential hydrocarbon gas zone was encountered between 950m and 1,150m with elevated values of methane, ethane, propane and butane identified on the mud log. Elevated gas levels were also intersected below 2,300m but only contained carbon dioxide.

The forward plan is to plug back the deeper zone, run wire line logs and based on these results test the hydrocarbon potential of the shallow zone.

Subject to a successful test, a distribution and marketing network of pipelines for a fast and economical way to monetize the potential discovery is present within 3km. Armenia is a net importer of natural gas, imports were 1.685 billion cubic meter in 2005.

Tags: Transeuro Energy Corp




   

Add a Comment to this Article

Please be civil. Job and promotion will not be added into the comment page.

(Use Markdown for formatting.)

This question helps prevent spam:

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us

 

sitemap xml


 

Home