Accident at South Korea’s Samsung Yard Delays Martin Linge Project


Published Jul 7, 2017
[an error occurred while processing this directive]

Edit page New page Hide edit links

Total logo

Following the tragic accident at the Samsung Heavy Industries (SHI) Geoje yard in South Korea on May 1st, 2017, Total has assessed the status of some of its projects given that the yard is being used for construction works related to three of its major projects: Martin Linge (Norway), Egina (Nigeria), Ichthys (Australia).

“We are deeply saddened by the accident that occurred at the yard on May 1st. Our thoughts are first and foremost with the families and colleagues of the victims who lost their lives or suffered injuries. Total has dispatched its experts to join the ongoing investigation to identify the fundamental causes of the accident and implement the necessary preventive measures to avoid any reoccurrence of such accidents. All works at the yard were suspended for several days in order to give absolute priority to the investigation, provide psychological support to the workers and review lessons learned before restarting activities,” says Arnaud Breuillac, President, Exploration & Production at Total.

Following the accident, works related to the Martin Linge project were suspended until June 1st. As a result, the shipping of the Martin Linge modules from the South Korean yard to Norway will be delayed. The installation of the modules and lifting operations, which can only be carried out during summertime given weather conditions in the Norwegian North Sea, had initially been planned for summer 2017 but have now been postponed to summer 2018. Therefore, given the hook-up and commissioning operations, production start-up has been delayed to first half 2019. The Martin Linge oil and gas field is located in the North Sea approximately 180 kilometres west of Bergen, Norway. The project partners are Total E&P Norge (51% operator), Petoro (30%) and Statoil (19%).

Work on the Egina FPSO resumed following a two-week suspension and the impact on the project, which is expected to start up in second half 2018, will be limited. The Egina development is located on deep offshore Block OML 130 approximately 150 kilometres off the Nigerian coast. Project partners are Total (24% Operator), CNOOC (45%), Petrobras (16%) and Sapetro (15%).

Finally, the CPF (Central Processing Facilities) for the Ichthys project, operated by Inpex, had already departed the Geoje yard several days before the accident and is now installed on the field in offshore Australia. The start-up of Ichthys, in which Total holds 30% alongside Inpex (62.245%), has therefore not been impacted by the accident and is scheduled for the first quarter of 2018.

Tags: Samsung Heavy Industries (SHI), Total




Advertisment:

Comments on this page are closed.

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us
Stats

 

sitemap xml