Sea Installer Crane Upgrade Complete


Published Jun 30, 2016
[an error occurred while processing this directive]

Edit page New page Hide edit links

Damen Sea Installer
A2SEA-owned jack-up leaves Damen Shiprepair Amsterdam able to handle bigger offshore wind installation projects (photo: Damen)

Damen Shiprepair Amsterdam (DSAm) has concluded major modification works on the Sea Installer. The principle scope of work involved the extension of the main crane boom, giving the A2SEA-owned offshore wind farm installation vessel increased reaching capacity: a pertinent point considering the trend of the increasing size of offshore wind turbine components. Other work comprised structural modifications as a consequence of the larger crane.

DSAm, part of Damen Shiprepair & Conversion, began the work by removing all crane-related components including the boom, boom rest, A-frame, winch and hook block pockets from the vessel. A2SEA supplied the new A-frame and boom extension. Niron Staal, also part of Damen Shiprepair & Conversion, supplied the new boom rest, hook block pockets, trolley rail and support stools.

The crane boom was lengthened by inserting the new extension. The fact that all elements were composed of high tensile S690 steel had its consequences to the timing of the project. Damen Junior Project Manager Remco van Dam informs: “This material requires distinct and carefully planned procedures. You can cut it when it’s cold, but, before you weld it, you need to heat it with heating elements to 200° C to remove any traces of water. Then, after slight cooling, the welding itself needs to take place at the correct temperature in a protected environment. For this, we constructed air-tight welding tents.”

Once complete, the weld in question was cooled prior to non-destructive testing after 48 hours: “We also performed our own initial checks after 24 hours in case any additional welds were needed. The main point with S690 is that you cannot rush things. If you go too fast, it can set you back 3 days.”

Installing the larger crane on the Sea Installer had numerous implications on existing on board structures. The boom rest had to be replaced, which in turn necessitated additional modifications to the accommodation area. In order to house the main hook and auxiliary hook in both long and short mode, the existing auxiliary hook block pocket was replaced with a new construction that comprised one main and two auxiliary hook block pockets.

The bigger crane also needed a bigger winch: DSAm replaced the existing winch with a larger, 900-tonne capacity, winch. This included all the necessary adjustments of the electrical, hydraulic and cooling systems. The vessel’s main mast also needed structural modifications.

The smooth running of the entire project was facilitated by the joint efforts of the DSAm and A2SEA personnel. “It has been a pleasure to work with the ship’s crew,” concludes Mr Van Dam. “There has been good communication throughout and this has helped us in many ways. For example, their involvement in adjusting the ship’s ballast tanks during such a heavy lift was crucial.”

Tags: A2SEA, Damen Shiprepair Amsterdam




Advertisment:

Comments on this page are closed.

+ Larger Font | + Smaller Font
Top Stories

 

 

 

 


 


RSS

RSS
Newsletter
Newsletter
Mobile News
Mobile news

Computer
Our news on
your website


Facebook
Facebook
Twitter
Twitter

Contact
Contact
Tips
Do you have any
tips to us
Stats

 

sitemap xml